Skip to content
Arc Flash Safety

Significance of Arc Flash Risk Evaluation and Mitigation Techniques - Carelabs Vietnam

By Carelabs Engineering Team
CL

Once an arc flash evaluation has produced numbers, the question changes from how much energy is present to what should be done about it. This is where most programmes stall, because the options are rarely compared on the same terms and the decision defaults to buying heavier PPE.

What the evaluation gives you to work with

The evaluation produces incident energy in cal/cm² at each working position, the arc flash boundary, and the PPE required to work there. Those figures turn a general concern into a ranked list, which is what lets mitigation spending be directed at the three worst locations instead of spread evenly across an installation.

It is worth being clear about what drives the number. Incident energy scales roughly with the duration of the arc and with fault current, but duration is the term with real leverage. Halving clearing time roughly halves the energy. Reducing fault current, by contrast, is usually difficult, expensive, and works against other objectives. Almost every effective mitigation is therefore an attack on time.

The techniques, compared honestly

Lowering instantaneous pick-up. The cheapest intervention: a setting change on the upstream device so it clears fast for a fault in the region of concern. Costs nothing in hardware. Costs selectivity, because the same device now also operates for downstream faults it should have let the local breaker handle.

Maintenance switching. A reduced setting engaged only while work is in progress and restored afterwards. Preserves normal selectivity and gives fast clearing when it matters. Depends entirely on discipline: an unengaged maintenance mode provides exactly nothing, and this is the most common failure of an otherwise sound programme.

Optical arc flash relays. Light sensors inside the switchgear detect an arc and trip in a few milliseconds rather than waiting for overcurrent grading to play out. The most effective single measure for existing switchgear, and largely independent of grading. Requires installation inside the panel and periodic testing, which is where neglected systems quietly stop working.

Current-limiting fuses. Cut both the magnitude and the duration of let-through energy within their limiting range. Very effective where they apply, though the range matters and they must be correctly coordinated.

Zone selective interlocking. Lets a device trip fast for a fault in its own zone while retaining selectivity for faults further downstream, by communication between devices. Resolves much of the selectivity-versus-speed conflict, at the cost of wiring and commissioning complexity.

Remote racking and remote switching. Does not reduce energy at all. Moves the person out of the boundary, which for racking operations is often the more practical answer than trying to make the operation survivable.

Arc-resistant switchgear. Directs blast products away from the operator, but only with doors closed and latched in the tested configuration. It is not a solution for work performed with the panel open, which is the condition most assessments are concerned with.

PPE. The last layer, not the first. Above roughly 40 cal/cm² arc-rated clothing stops being a credible control, because the pressure wave, projectiles and acoustic injury are not addressed by thermal rating. A high calculated figure is an instruction to re-engineer the installation.

The cost that justifies the work

For an export-oriented plant, the economic case rarely rests on the injury alone, severe though that is. It rests on what follows: an investigation, a stopped line, the regulatory involvement that follows a serious electrical incident, and the customer audit that tends to arrive shortly afterwards. Facilities supplying international buyers are routinely audited on safety management, and an unquantified electrical hazard is a finding that is both easy for an auditor to identify and awkward to close quickly.

Against that, most mitigation is inexpensive. Setting changes cost engineering time. Maintenance switching costs procedure and training. Optical relays cost hardware on the panels that need them, which is normally a small subset.

Keeping controls alive

Mitigation decays quietly. A maintenance mode nobody engages, an arc flash relay nobody tests, labels calculated against a fault level EVN has since increased. Each of these leaves a programme that appears complete on paper while providing progressively less protection. Controls need to sit in the maintenance schedule alongside the equipment they protect, and the evaluation needs re-running whenever the source, the settings or the network configuration change.

The regulatory framing in Vietnam supports this: the Law on Occupational Safety and Hygiene 2015 places a continuing duty on the employer to identify and control hazards, not a duty discharged once. TCVN 7447 governs the installation and QCVN 01:2008/BCT the electrical safety requirements, and DOLISA looks for evidence of a live programme rather than a historical document.

Related reading: arc flash analysis produces the figures discussed here, and the clearing times every technique above depends on come out of relay coordination.

VNElectrical Safety

Frequently Asked Questions

For most existing installations, maintenance switching and optical arc flash relays. Both attack arcing duration, which is the term with the most leverage over incident energy, and neither requires replacing switchgear. Setting changes are cheaper still but cost selectivity, so they suit locations where the grading consequence has been assessed and judged acceptable.

No. Its rating applies with doors closed and latched in the configuration it was tested in, so it protects against a fault occurring while the panel is secure. It does not describe the exposure once the panel is opened for testing or fault-finding, which is the condition most arc flash assessments are concerned with in the first place.

Put the controls in the maintenance schedule rather than the project file. Arc flash relays need periodic testing, maintenance switching needs to appear in the permit procedure so engaging it is not optional, and the evaluation needs re-running whenever fault level, protection settings or network configuration change. Undocumented drift is what makes old studies misleading.

Need Expert Electrical Safety Support?

Carelabs provides arc flash studies, power system analysis, and TCVN 7447 compliance services across Vietnam.