Skip to content

IEEE 1584 · Engineering

Load Flow Analysis

Load flow analysis solves the steady-state operating condition of your power system — node voltages, branch power flows, real and reactive power, and line losses — for a specified generation and network configuration. For a Philippine facility this means confirming your network can carry required loads during planned outages without exceeding rated capacity, and identifying where reactive power compensation and transformer tap settings should sit for efficient operation. Carelabs performs the study in ETAP, modelling your network as nodes connected by impedances and solving it iteratively, and delivers findings aligned with the Philippine Electrical Code.

Free Consultation

Before you commit to the expansion

Adding a line, a chiller or a production cell is an electrical question before it is a commercial one. Load flow answers whether the installation carries it, at what voltage, and what breaks first if it does not.

What We Deliver

The planned load as its own case

New load is modelled as a distinct scenario including motor starting where large drives are involved, so the answer covers the plant you intend to run rather than only the plant you have.

WHY IT MATTERS

Capacity discovered after the order

The expensive version of this question is asked after equipment has been purchased and a constraint appears during commissioning. The cheap version is asked while the specification is still a document.

  • Demand established from metered data rather than connected load, because the difference between the two is where capacity misjudgements begin.
  • Motor starting assessed where significant drives are added, as starting current depresses bus voltage for its duration and can trip sensitive equipment elsewhere.
  • Alternative switching arrangements studied, since a network comfortable in the normal configuration can be constrained on the standby one.
  • Standby generation modelled separately where present, because generator impedance and capacity differ substantially from the utility supply.
  • Reactive compensation checked for resonance against existing harmonic content before it is recommended rather than after it is installed.
Contact Us

DELIVERABLES

What you receive

Issued against the Philippine Electrical Code with the load basis and modelling assumptions stated explicitly.

  1. 1Bus voltage table per scenario with deviation from nominal against the applicable limit
  2. 2Branch loading summary identifying every element above rating and the margin on those approaching it
  3. 3A stated spare capacity figure at the constraining element, in kVA
  4. 4Losses by branch, so compensation and reconductoring can be targeted
  5. 5The calibrated ETAP model, so the next expansion is a re-run rather than a new engagement
Reach Out

How the study runs

01

Define the question

We agree what the study must decide: whether a planned load can connect, why voltage is low somewhere specific, or how much headroom remains before reinforcement.

02

Establish the load basis

Metered demand is collected where available and reconciled against connected load, which is usually where the useful finding sits.

03

Build the network model

Transformers, cables and busbars are modelled in ETAP from verified data, with impedances from test certificates where those exist.

04

Run the scenarios

Each agreed operating case is solved, including alternative switching arrangements and any standby supply the site can run on.

05

Identify what binds

The constraining element is identified per scenario along with its remaining margin, which is the number capacity planning needs.

06

Report and options

Findings are issued with reinforcement, reconfiguration and compensation options, each with the constraint it relieves and the one it does not.

Frequently asked questions

Maximum demand tells you how much you draw, not whether the network delivers it everywhere at acceptable voltage. Load flow locates the constraint, which is frequently a feeder or a switching arrangement rather than the transformer. It also identifies what binds next once the present constraint is relieved.
Earlier is better and cheaper. Modelling a planned load while it is still a specification allows the electrical constraint to influence the equipment selection. Once equipment is ordered the options narrow to reinforcement, which is usually the most expensive way to resolve a problem that was foreseeable.
Where it exists, yes, as a separate case. Generator impedance and capacity differ substantially from the utility supply, so a load that is comfortable on normal supply can be constrained on standby. Sites frequently discover this during an outage rather than during planning.
The same verified network supports short circuit, arc flash, protection coordination and harmonic studies. Capturing and validating the network is the largest component of cost in any of them, so retaining the model means later questions are answered in days rather than through a repeat survey.

Schedule Your Load Flow Analysis

Tell us about your project.